Northumberland Rail Station, North London – Cladding Panel Repair & Respray

Northumberland Park is a busy London railway station serving the Tottenham area.

Project Spec

Commencement date: November 2018

Completion date: November 2018

Labour: Two operatives for one night and two days

Scope of Works

To refurbish several panels on two platforms.

To mask and protect all areas unaffected by damage.

Clean and prepare all deep scratches and dents for filling and priming.

Fill and prime all scratches and dents.

Remove excess filler and smoothen panel surface.

Apply topcoat in RAL7000.

Method & Special Requirements

Scaffold Tower required to reach works at height.

Painting of panels to be completed once panels have been prepared, primed and repaired, requested painting technique is spraying.

Due to the position of some of the panels it was necessary for works to be completed during a possession of the line, these panels were completed overnight.

PASMA ticket for erection of Scaffold Tower.

Buckingham Coatings commissioned for cladding panel repair work

Our team was called in to repair and respray several damaged cladding panels at the railway station.

Working alongside a number of other contractors on the site, Buckingham Coatings operatives would be required to work on a challenging project requiring the repair and respray of several damaged cladding panels on two platforms.

Cladding remedial work in exceptional conditions

This project required an exceptional regard for safety due to the conditions in which our team was working.

The Buckingham Coatings team not only had to negotiate a close working relationship with several contractors involved in the railway station’s ongoing groundworks. We also had to conduct the job at night, when the line was closed, working at height.

Strict health and safety compliance

Our work to refurbish several cladding panels on the station platforms required us to work at height using scaffold tower equipment.

Our operatives hold Prefabricated Access Suppliers’ & Manufacturers’ Association (PASMA) tickets, which provided the necessary evidence of their full training in use of this equipment that suitably complied with the strict health and safety rules of the site.

Despite having to work night and around so many other contracted workers, with a little extra care for safety and coordination with the groundworks’ teams, we were able to carry out the cladding panel repair and respray works as efficiently as normal.

Cladding coating in requested RAL colour

Once the affected areas of cladding had the scratches and dents filled and primed, they were coated in colour-matched RAL7000 “Squirrel grey” colour by our paint spraying operatives.

Another successful cladding panel repair & respray

The cladding remedial works were complete in one night/ two days, successfully delivering to the high safety spec and with a high-quality finish.

Contact us about improving your building’s cladding or signage

If you have any signage, cladding or facades that require cleaning, repairing or recoating then please contact us for information or a quote.

Tel: 01376 311597

or email: info@buckinghamcoatings.co.uk

Recent News

Check out some more of our most recent news:

JCB Cladding Repair – Cambridge

JCB Cladding Repair - Cambridge Buckingham have recently completed a cladding repair project for JCB in Cambridge, this project was carried out over the course of two days and required

What do our Accreditation’s mean?

What do our Accreditation's mean? You've seen our accreditation certifications dotted about our website here and there.. but what do they all actually mean? We've summarised each of them here

Burger King, Telford – Cladding Repair & Respray

Burger King, Telford - Cladding Repair & Respray Our client contacted us requesting cladding panel repairs after selected areas receiving damage. During this project, we had to complete an on-site

Interested in working with Buckingham Coatings on a project like the above? Get in touch today to discuss your requirements.

Contact Us